Project Description

Beny Sweif is one of the giant projects in the field of the Electro Mechanical contractions for GLOBAL Company power station with a 48 MW capacity for Ganob Al Wady Cement Factory that is consisted of various installations which contained the installation of 8 Transformers 2500 KVA each and Medium Voltages panels (RMU) control panels & 1200 meters of medium Voltage Cables, 2400 meters of low voltage cables and 4500 meters of Control cables were installed. And connected to all the above, 8 caterpillar Gensets 2000 KVA each were installed .The installation was as preformed as follows.The first power station had a capacity of 24 MW and was upgraded to 48v M Watt due to planet requirements, the Factory had to install a second power station that shares the same capacity for the total capacity of the two stations together to be 48 MW by synchronizing both stations together as each station consists of 8 2000 KVA caterpillar Genset generators each generator is connected to a Transformer that all transformers are synchronized together on medium voltage scale.

Case Details

Client
Global Energy
What We Did
48 M watt power plant constructions
Location
Beniswif
Client Paid
EGP

More Details

Project including designing,  installing, test and commissioning start up of:

  • Medium Voltages panels (RMU)
  • 24 Genset Caterpillar 3516
  • 8 Transformers 2500 KVA each
  • Medium Voltage Cables, 2400 meters
  • Low voltage cables and 4500 meters of Control cables
  • Synchronizing control
  • Nam lobortis vulputate urna quis faucibus.

Resources Used

Marketing

Analytics

Marketing

Professionals

Finances

Managers

Ready to build the Substation of your biggest dreams?
Let’s get started today, you won’t regret!

Browse Services